The first phase of the Envision Xinghe Base, with a capacity of approximately 200MW, was fully delivered by the end of October.

A SemiAnalysis on-site visit reported that the first 120MW of the Envision Xinghe base in Inner Mongolia was built and delivered in less than 1 year, and the approximately 200MW first-phase project was fully delivered by the end of October. The park plans to reach 800MW of IT power supply capacity by the end of 2027.