Satellite imagery shows Microsoft AI data center partner IREN and Nebius projects may be delayed

PANews November 5 reported that, according to Business Insider, satellite imagery analysis by research firm Aterio shows that IREN in Texas for Microsoft, under an approximately 9700000000 USD agreement, the Horizon 4 data center still lacks backup generators and cooling equipment, creating a risk that it cannot be delivered by year-end; the New Jersey project being developed for Nebius, with planned capacity of approximately 140000000 watts, may be delayed until 2027. Microsoft’s AI related capital expenditures last quarter were approximately 5000000000 USD below expectations, and it lowered its full-year guidance.CFO previously cited delivery delays by third-party cloud service providers as one of the main reasons; a Microsoft spokesperson said its infrastructure strategy remains flexible,IREN and DataOne declined to comment.