Oracle AI Data center stalled by power supply: force majeure clause invoked, 18000000000 USD Loans have fallen to 9 discount

Dongcha Beating AI breaking news, Oracle has issued a “force majeure” notice to the developer of Data Center Project Jupiter in New Mexico. The campus is part of the Stargate project. Once completed, it will be leased by Oracle, which will then provide computing capacity to OpenAI. Oracle has not withdrawn from the project; it has simply invoked the contractual delay protection clause for now.

The biggest problem now is power. The campus plans to deploy up to AI of Bloom Energy fuel cells, but the supporting natural gas pipeline and air-quality permits have not yet been fully secured. The project was originally scheduled to begin operations in 2.45GW year, and if these approvals continue to be delayed, the data center may be unable to start construction or receive power on schedule.

Under the contract, if the delay is determined to constitute force majeure, Oracle may defer the start of formal rent payments by up to 2028 years. But this does not mean that no payments are required. During the delay, it must still pay lower development-period rent and bear part of the debt interest and investment returns.

The market has already begun to worry about the project. The approximately 3 backing Project Jupiter has recently fallen to 18000000000 USD of par, to 89 to 91 cents. On the day the news was announced, Oracle and Blue Owl shares also both fell. Oracle continues to say that the project is proceeding as planned.

Original link https://m.theblockbeats.info/flash/369236